Tourle St Bridge
September 2008 - May 2009
Client Information
RTA of NSW
- Duration: 9 Months
- Value: $30.3 million
- Location: Mayfield West- Kooragang Island
-
Project Details
Scope of Work
- Construction of bridge including:
- Tubular steel piles
- Abutments
- Reinforced concrete piers
- 255m, 8 span prestressed concrete girder bridge
- Traffic barrier railings
- Road pavements
- 300mm stormwater & 600mm watermain
- Earthworks including pre-consolidation of soils and construction of embankments,680m of approach road works
Significant Achievements
- The project is expected to be completed approximately 10 weeks ahead of schedule
- An innovative girder launching system was utilised on the project to overcome practical limitations. A purpose-built 70m long, 130t gantry was employed to place girders for the bridge, which also provided a high level of precision during placement
- An underground bentonite cut-off wall was constructed on the Southern approach to prevent spread of existing industrial waste contamination (benzene plume) into the adjacent groundwater and surface water systems
- Steel casings were installed prior to the driving of concrete piles as protective sleeves to prevent the surrounding contaminated soil and groundwater making contact with the piles
- Extensive planning was required to coordinate and allow watermain relocation, approach works, and bridge works to be carried out simultaneously
- Various sacrificial anodes were installed to provide the pile, abutment and pier concrete with cathodic protection from the surrounding marine environment
- Due to existing high traffic volumes, complex traffic management issues were successfully overcome through the staging of approach works, construction of temporary sidetracks, and implementation of various traffic restrictions