April 2001 - April 2002

Client Information

Old Windsor Road Duplication

  • Duration: 12 months
  • Value: $5.1 million
  • Location: Stanhope Gardens, Kellyville
  • Project Details

Scope of Work

  • Flexible pavement placed over lean mix sub base
  • Major intersection with traffic lights built at Samantha Riley Drive
  • Work included all services, drainage, landscaping and cycleway

Significant Achievements

  • Work program constrained by commitment for early completion of Samantha Riley Drive interchange half way along work.
  • Detailed traffic switches were done often to provide for minimum impacts on 50,000+ ADT volume and maintaining safety of those working on site.
  • 25,000m2 of lean mix sub base 240mm thick was successfully hand placed by subcontractors De Martin Gasparini and achieved the tight time, cost and quality requirements of the specifications.
  • Several heritage boundary stones circa 1825 were identified along the route, were protected then carefully relocated.
  • Two large water mains (900mm and 500mm dia) were re-laid across the site without incident or disruption.