Mine Infrastructure Installation and Maintenance

2005, ongoing through into 2011

Client Information

Coal & Allied

  • Duration: 6 years and ongoing
  • Value: Total $10 million
  • Location: Various Rio Tinto Coal Mines across the Hunter Valley
  • Project Details

Scope of Work

Work for this project involved building and maintaining various mine facilities including haul roads, access tracks, water re-fill structures and environmental controls

Significant Achievements

  • Road maintenance and drainage works
  • Construction and maintenance of haul roads and access roads throughout the mine sites
  • Installation of drainage structures
  • Restoration and repair of drains and other structures
  • Concrete structures including culverts, headwalls and aprons
  • Installation of gabion baskets
  • Construction of mine support facilities e.g. water points, pipe lines and environmental controls