Mac Mine Worker Village
March 2011 - July 2011
Client Information
The Mac Group
- Duration: 16 weeks
- Value: $1.4 million
- Location: Narrabri, North West NSW
-
Project Details
Scope of Work
The Mac Mine Worker Village project included the civil works associated with the construction of the first stage of a mine worker village at Narrabri. Work commenced in December 2010 and was completed in March 2011.
Significant Achievements
- Work completed within client required timeframes despite wet weather
- Over 800t asphalt wearing course
- Surface and subsurface drainage works
- 1.5km kerb and gutter
- Bulk earthworks and village building pads
- Use of laser buckets, ATS and GPS controlled plant
- 12,000t pavement
- 10ML detention basin and drainage blanket
- Concrete works including multi-cell cast in-situ headwalls, wingwalls, encasement slabs and aprons.