Kooragang Coal Export Terminal 3

Completed July 2009

Client Information

Newcastle Coal Infrastructure Group

  • Duration: 18 months
  • Value: $35 million
  • Location: Kooragang Island
  • Project Details

Scope of Work

  • Site compound establishment an d infrastructure
  • Preliminary earthworks
  • Sand reclamation / dredging works
  • Haul roads construction
  • Car parks, preliminary internal roads and drainage
  • Potable water and sewer
  • Concrete foundations / footings and  slabs
  • Concrete drainage structures and culverts

Significant Achievements

  • Gaining client confidence of the Daracon Group advantage (focused people, focused outcomes).
  • Utilisation of Daracon’s diverse company personnel and resources.
  • Overcoming a number of design obstacles and omissions and working together collaboratively with Client to gain a positive outcome for all stakeholders in very quick time.
  • Excellent OHS record, with over 200,000 man hours worked without an LTI (Lost time injury).