Drayton Stacker Trail Rail Replacement

March 2011

Client Information

Anglo Coal (Drayton Management) Pty Ltd

Scope of Work

  • Removed the corroded clips and replace with the newly procured galvanised e-clips prior to rerailing works including new nylon sleeper pads.
  • Clean up and removal of coal spill shall from the stacker tracks

Significant Achievements

  • Works completed on time and budget working with Anglo Coal Draytons to minimise down time to the Stackers
  • Zero LTI, FAI or MTI’s on the project
  • Working in and around a live stacker during coal clean up and prep works.
  • Identifying cost and scope reductions to Anglo Coal Draytons resulting in cost savings being given back to Anglo.