Cowpasture Road Reconstruction

Client Information

RTA, NSW

Scope of Work

  • All work done under heavy traffic
  • Stormwater drainage
  • Electrical services
  • Public utilities
  • Power
  • Telephone
  • Water

Significant Achievements

  • Cowpasture Road is a major arterial road that carries over 50,000 vehicles per day.
  • The project required the construction of two additional lanes that were used while the existing carriageway was rebuilt.
  • Traffic management was a critical aspect of the project.  All work was done under traffic with minimal disruption to traffic flow and no incidents.
  • Many traffic changes were necessary to accommodate the numerous construction stages and these were often done overnight when traffic volumes were least.
  • The site adjoins the Western Sydney Regional Park, an Olympic Equestrian venue, which is a sensitive environmental site.  Special work processes were put in place to ensure that environmental aspects were carefully controlled.
  • Consultation with the community was a continuous process throughout the project and covered a range of issues including traffic changes, vibration monitoring and building condition assessments.
  • Major sewer and water infrastructure required relocation and this was carried out by Daracon personnel who are accredited by both Sydney and Hunter Water Corporations.