Carrington West Wing Water Management
February 2006 - May 2006
Client Information
Coal & Allied
- Duration: 4 months
- Value: $1.7 million
- Location: Hunter Valley Operations
-
Project Details
Scope of Work
110,000m3 of earthworks to construct flood levels. 2km of rock lined drains. Twin cell Ø1800 and Ø1500 lecor culverts.
Significant Achievements
This was one of the first major projects Daracon undertook in the mining industry.