Breakfast Point Subdivision
2002 - 2004
Client Information
Jeff Moulsdale and Associates (Hyder Consulting)
Scope of Work
- Bulk Earthworks which included 90,000m3 cut to fill, majority being sandstone.
- Construction of infrastructure which included, sewer, water, electrical, stormwater, Telstra and gas
- Flexible pavement construction approximately 2km roads
- Construction of a seawall on the north and east perimeter
- Installation of retention tanks and GPT’s used for irrigation
- Management of stormwater runoff including treatment and disposal of overfilled basins
Significant Achievements
- The site is surrounded by the Parramatta River, which required all works to be completed with protection of run off and pollution, which was successful.
- Completing the project within the time constraints required by the client.
- Successful construction management of remediated areas along the foreshore.
- Recognition from the client for our efforts by awarding more work on the project.