Baal Bone Colliery
2 months, and than a further 3 months - completed 2006
Client Information
Wallerawang Collieries Ltd
- Duration: 2 months, than a further 3 months
- Value: $500,000
- Location: Baal Bone Colliery, Lithgow
-
Project Details
Scope of Work
- Load, crush and screen feed coal to <50 mm
- Raw coal taken from underground discharge stockpile and stockpiled separately nearby
Significant Achievements
- Production at >3,000 tonnes per day
- All plant passed inspection to mine’s standard at first attempt
- Product quality exceeded customer expectation
- Production rate exceeded customer expectation
- The client initiated a second contract for a 3 month period
- Plant availability >95%
- There has been close cooperation between Baal Bone and Daracon personnel
- There has been no lost time injuries, medical treatment or first aid incidents during the work
- There has been no environmental or industrial events