Roads

What We Have Achieved

Aberdeen Track Formation Reconditioning

4 months, completed May 2011

Client Information

ARTC

Scope of Work

Recondition of 80m of track, with replacement of existing pipe culverts with cattle grid culverts.

Significant Achievements

  • All works completed within 4 day track shutdown.
  • Overcame difficult site access for installing cattle grid culverts by using a 300 tonne crane.