Coal Export Pad Extension
View Project Detail
Daracon completed the construction of 17 km Haul Road from the mine to the rail loading facility including two local road intersections and crossing the Namoi River and Kamilaroi Highway
The relocation of 6km of Castlereagh Rd with associated tie ins to the existing road network at six locations
Upgrades to Cessnock Road
Construct 1.3km of 4 land road
Construct 3 earth filled dams to control water run-off from the Mt Arthur mine site.
7.4km final stage to link Sydney and North Coast
Construction of interchange
Construct additional dual carriageway; entry/exit ramps; pedestrian overbridge; stormwater structures
Underpass of the rail line on Metford Rd
6km of 4 land dual carriageway roadwork
Replace an intersection with a multi level interchange of two major arterial roads in Sydney’s north west
Constructed 1.5km dual carriageway section of road to replace existing lower standard carriageway.
Construction of Bridge
Coal Loader Expansion
Daracon implemented environmental control measures as well as works which included clearing, stripping and site preparation for filling, preload foundation, fill and compact and concrete structures.
Expansion of the Port Waratah Coal Loader
Infrastructure Works for Future Coal Loader
Footings, suspended concrete tub sections for conveyor lines, additions to existing structures and drainage works.
Intersection at Blue Vale and Shannon Harbour Road
Lay 29km of 300mm DICL water main between Tomago and Bobs Farm
Construct a 3.7Km, 4 Lane upgrade to Windsor Road